An order for 50 of a product is processed on world centers a and b. the set up time on a in 60 minu

An order for 50 of a product is processed on world centers A and B. The set up time on A in 60 minutes, and run time is 5 minutes per piece. The set up time on B is 30 minutes and the run time is 6 minutes per piece. Wait time between the two operations is 10 houses. The move time between A and B is 60 minutes. Wait time after operations is 10 houses. The move time into stores is 2 houses. The move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 35 hours. Calculate the total manufacturing lead time for the order. And also calculate the total manufacturing lead time for the order
midhun
Asked Jun 27, 2012

TIP: If it's not your answer to this question, please click "Leave a Comment" button under the question to communicate with the question owner.

Categories